The operation of two hydropower plants in Valbona has finally stopped following the enforcement of a ruling by the Albanian...

The operation of two hydropower plants in Valbona has finally stopped following the enforcement of a ruling by the Albanian...
The enforcement of the High Court Decision against Genr2, which have constructed two hydropower plants in Valbona, is now being...
A Tropojan bailiff has reportedly refused to execute a court order against hydropower plant construction company Genr2. In July 2021,...
WWF Adria has condemned the continued construction of hydropower plants in Valbona by Dragobia Energy and Genr2, despite a decision...
Following yesterday’s High Court decision which stated Gener2 and Dragobia Energy must suspend all construction on two hydropower plants in...
“When hiking through the country, if you come across a stream or river, you must always cough before you get...
The Administrative Court of Appeals will review in September the lawsuit of the concession company "Seka Hidrypower" to produce electricity...